Dear Friends,
This is regarding Structural steel erection for process plant in Hydrocarbon (Oil & Gas)
1. Pipe Rack (21 m Height)
2. Technology structure (24 m)
3. Compressor shelter (15)
4. Sheeting
Can anyone will be able to guide me in planning for crane requirement. How many number of cranes are required to erect per day. may be in terms of Tons / Day. Crane productivity can be so many tons / day in erection, so many tons / day in material handling for erection.
Regards,
Kumar
This is regarding Structural steel erection for process plant in Hydrocarbon (Oil & Gas)
1. Pipe Rack (21 m Height)
2. Technology structure (24 m)
3. Compressor shelter (15)
4. Sheeting
Can anyone will be able to guide me in planning for crane requirement. How many number of cranes are required to erect per day. may be in terms of Tons / Day. Crane productivity can be so many tons / day in erection, so many tons / day in material handling for erection.
Regards,
Kumar