Dear Sirs.
I have a project in KSA where during the one months
project working Hr just 6 Hr./day and other months are normal 10 hr/day for Labours.
however schedule is Resource Loaded , i have modify the Cal. mark 6 hr/day during this month but cal assign to Res is 10hr/day.
some activity having duration 35 days 60 days 90 days
these activity will be under progress during this months.
Please advise how i can reslove this problem.
Thanks & Regards