Good Monig. Mr Rodel
I have an activity 10 days duration max.working Hr 10/d
This activity having four resources 2 nonlabour and 2 labour,
activity name is Foundation, OD 10 days. ( cal 6D/week)
Resource , 1 Execavator Nonlabour.
2. Execavator Operator (labour)
3. Roller Operator (labour)
4. Roller (nonlabour)
first 5 days for excavation, and last five days for Rolling,
i assing these resourece to avtivity all resource are over alocating,
Please advise me how i can assign these resource to activity avoid the resource over allocating.
How many units i have to allot for each resource.
Thanks & Regards
I have an activity 10 days duration max.working Hr 10/d
This activity having four resources 2 nonlabour and 2 labour,
activity name is Foundation, OD 10 days. ( cal 6D/week)
Resource , 1 Execavator Nonlabour.
2. Execavator Operator (labour)
3. Roller Operator (labour)
4. Roller (nonlabour)
first 5 days for excavation, and last five days for Rolling,
i assing these resourece to avtivity all resource are over alocating,
Please advise me how i can assign these resource to activity avoid the resource over allocating.
How many units i have to allot for each resource.
Thanks & Regards