Hi every one,
By defult physical % complete is not rolled up in P6. However I have noticed some planners use a workaround to roll up physical % complete and use it to measure the rolled up progress.
While rolled up progress can be calculated using unit % complete or duration % complete in P6, what is the advantages of using rolled up physical % complete that the other two % complete type do not have.
I appriciate any explanations or examples.