Running MSP 2007
Im trying to use MSP to report Earned Value metrics, without resource loading it.
I thought I would enter costs as fixed costs, baseline, then at each update enter actual costs and adjust the remaining costs, much like I would enter actual duration, and adjust remaining duration.
But I cant find a way to manually adjust the remaining cost.
It seems to work OK if I adjust the fixed cost column instead of remaining cost, but this feels like a bit of a fudge to me.
What am I missing?
Thanks,
G