Hi All,
How do the various departments within the company handle the following Calendar issues in Primavera?
1.Projects department require a calendar of 8hrs per day 5 days per week for all FEED office work;
2.Operations require a calendar of 24 hrs per day 7 days per week for TA related work;
Do you set up a global calendar of 24/7 or 8/5?
Do you set the Global calendar to 24/7 or 8/5 and then tell the various departments to use a Project Calendar with the correct hours per day?
Any useful information in solving this issue will be appreciated.
Thanks and Regards.
How do the various departments within the company handle the following Calendar issues in Primavera?
1.Projects department require a calendar of 8hrs per day 5 days per week for all FEED office work;
2.Operations require a calendar of 24 hrs per day 7 days per week for TA related work;
Do you set up a global calendar of 24/7 or 8/5?
Do you set the Global calendar to 24/7 or 8/5 and then tell the various departments to use a Project Calendar with the correct hours per day?
Any useful information in solving this issue will be appreciated.
Thanks and Regards.