Guys,
Im just wonder if we can do global change on "finish date column"
What I did, I imported the excel data onto user_end_date(my forecast date) I want to use global change something like this:
If user_end_date bigger than XXX
Then Finish date = user_end_date
but the problem is I didnt find "finish date" column instead planned finish date.
so is it we cant change the finish date automatically?
thx