My understanding of Auto compute Actual under Resource details tab is illustrate by an example , kindly correct me , if i am wrong......
For example i have an activity Excavation - and for this activity am putting 50% progress then P6 automatically assumes that 50% of the resource are also utilized for the activity (actual units) , if auto compute is activated (ticked) or else if i remove the tick or deactivate the icon , then i have to enter manually the resources utilization or actual units...
Kindly correc me , if my understanding is wrong....
regards,
Haresh Jayanth
For example i have an activity Excavation - and for this activity am putting 50% progress then P6 automatically assumes that 50% of the resource are also utilized for the activity (actual units) , if auto compute is activated (ticked) or else if i remove the tick or deactivate the icon , then i have to enter manually the resources utilization or actual units...