Hi everyone,
in p6 schedule I have:
1 - Four resources each with their own calendars
2 - Each resource is capable of doing certain tasks (e.g. activity 1 can be done by resource A and B, activity 2 by resource B,C, and D, etc.)
is it possible to have p6 to pick up a resource austomatically from a list of available resources for each activity?