Dear All,
We received Letter of Intent from the Client for a project and after that there was a Kick of meeting , wherein it was agreed the Project start date would be 12th May 2010.
But after the letter of Intent , the client delayed the finalization of contract for 2 weeks and no Letter of Award was issued during that time. Now we intent to change the project start date of the project from 12th May 2010 to 25th May 2010 (the date of finalziation of the contract), since we cannot finalize with our subcontract any agreement with out LOA or written acceptance......
So we are in the process of writing a contractual letter....can anybody suggest some useful tips ..which can be added in my letter for the above mentioned scenorio....
We received Letter of Intent from the Client for a project and after that there was a Kick of meeting , wherein it was agreed the Project start date would be 12th May 2010.
But after the letter of Intent , the client delayed the finalization of contract for 2 weeks and no Letter of Award was issued during that time. Now we intent to change the project start date of the project from 12th May 2010 to 25th May 2010 (the date of finalziation of the contract), since we cannot finalize with our subcontract any agreement with out LOA or written acceptance......
So we are in the process of writing a contractual letter....can anybody suggest some useful tips ..which can be added in my letter for the above mentioned scenorio....