Planners,
Query with reggards to Critical Path in P6.
If I do not link task dependent activity to finished milestones and schedule the project, it does not give me critical path. I suppose P6 gives you critical path as the longest chain of activities in a project and linking to a finish milestone is not a manadatory case.
Also, If I link activities to finsihed milestones & schedule the project, it automatically changes the finished milestone dates. In this case I do get the critical path but original milestone dates do not exist any more.
Anyone can explain how to get over this? Thanks.
Kandarp
Query with reggards to Critical Path in P6.
If I do not link task dependent activity to finished milestones and schedule the project, it does not give me critical path. I suppose P6 gives you critical path as the longest chain of activities in a project and linking to a finish milestone is not a manadatory case.
Also, If I link activities to finsihed milestones & schedule the project, it automatically changes the finished milestone dates. In this case I do get the critical path but original milestone dates do not exist any more.
Anyone can explain how to get over this? Thanks.
Kandarp