Kind Attn: Mr. Rodel
Dear all,
I have updated the baseline for the past 6 months, now client has made major modification in the baseline program. i have done all modifications in the baseline program and the revised baseline program is approved.
Now i would like to copy only the updated activities of my previous updated program and pasted into the new revised program.......
What is the shortest way of pasting this update in the new revised program. In p3.1 , this function "Update activites with matching IDs was very useful to me, in this type of Scenario.....What u suggest.............
regards,
Haresh
Dear all,
I have updated the baseline for the past 6 months, now client has made major modification in the baseline program. i have done all modifications in the baseline program and the revised baseline program is approved.
Now i would like to copy only the updated activities of my previous updated program and pasted into the new revised program.......
What is the shortest way of pasting this update in the new revised program. In p3.1 , this function "Update activites with matching IDs was very useful to me, in this type of Scenario.....What u suggest.............
regards,
Haresh