Gents,
Ive updated schedule and now I make it as baseline to the new schedule.
But the problem is some of baseline plan date slipped from the original and i realized it was the completed one(100%) for instance its completed on Apr but the date now extended to June.
Why this thing happen?
Ive updated schedule and now I make it as baseline to the new schedule.
But the problem is some of baseline plan date slipped from the original and i realized it was the completed one(100%) for instance its completed on Apr but the date now extended to June.
Why this thing happen?