Hi,
I have dealt in P3.1; two options in Scheduling i.e. retained logic and progress override. But P6 have one more options i.e. Actual Dates………What is the logic behind using actuals…..I have read from help menu that Actual Dates will schedule my backward and forward passes using actual dates.
I think Progress override is also of the same use. It will override my logic and use the actual progress to determine the progress of work……..Can anybody explain what is the exact use of “actual dates”
I have dealt in P3.1; two options in Scheduling i.e. retained logic and progress override. But P6 have one more options i.e. Actual Dates………What is the logic behind using actuals…..I have read from help menu that Actual Dates will schedule my backward and forward passes using actual dates.
I think Progress override is also of the same use. It will override my logic and use the actual progress to determine the progress of work……..Can anybody explain what is the exact use of “actual dates”