I have a tender request that I am dealing with just now and part of the planning section contains a request that I am not entirely sure of the best way to handle it.
The project is made up mainly of engineering and each section will contain 4 revisions the client wants the breakdown as follows - issue rev 1 60%, issue rev 2 10%, issue rev 3 10% and issue rev 4 20%. Of course with the 4 tasks under each wbs section as rev 1 completes and shows 100% it feeds up showing 25% complete of the entire task.
Is there anyway to roll up taking into account the weights mentioned?
Thanks in advance
David
The project is made up mainly of engineering and each section will contain 4 revisions the client wants the breakdown as follows - issue rev 1 60%, issue rev 2 10%, issue rev 3 10% and issue rev 4 20%. Of course with the 4 tasks under each wbs section as rev 1 completes and shows 100% it feeds up showing 25% complete of the entire task.