Can anyone tell me what setting is causing this to happen please? I am using task dependent activites, fixed units/time (duration type)
Example. I have an activity with 5 days duration, when I add one resource its fine, when I add the second its dividing the budgeted units by the number of recources in this case it becomes 2.5 if I were to add a third the budgeted units for each of the 3 recources would become 1.7.
I need to show 5 days for each of the recources.
Thanks in advance