Why does primavera read resources imported from excel as Labour although it is defined in primavrea as material and specified in excel in resource type as material as well
i want to import resources from excel to activities in primavera, every time i import i find in the price/unit field this symbol 0^ and primavera deals with it as labour
i came to know that becuase i found that the budgeted cost equals budget units * price/unit * 8 hours/day(working hours/day)
that means that the price/unit is actualy price/hr although i have defined this resource as Material and its unit of measure as each in both primavera & the excel sheet im iporting to primavera
Can someone help please
i want to import resources from excel to activities in primavera, every time i import i find in the price/unit field this symbol 0^ and primavera deals with it as labour
i came to know that becuase i found that the budgeted cost equals budget units * price/unit * 8 hours/day(working hours/day)
that means that the price/unit is actualy price/hr although i have defined this resource as Material and its unit of measure as each in both primavera & the excel sheet im iporting to primavera
Can someone help please