USE OF A DUMMY RESOURCE TO MODEL RESOURCE SHARING AMONG DIFFERENT SHIFTS
I am exploring the modeling of shifts in Spider Project and found that in order to constraint within a shift the use of a resource available 24 hours a day with the use of a dummy resource I can do that, is this a correct approach or is there any issue I might be missing?
The following is a print screen capture of what I am doing.
[1]
For your convenience you can download the file from the following link. You will need version 10.01.51 of the software full version or demo versions, released 20/04/2010 or a newer version.
http://rapidshare.com/files/378438789/SHIFT.001.sprj [2]
Best regards,
Rafael
I am exploring the modeling of shifts in Spider Project and found that in order to constraint within a shift the use of a resource available 24 hours a day with the use of a dummy resource I can do that, is this a correct approach or is there any issue I might be missing?
The following is a print screen capture of what I am doing.

For your convenience you can download the file from the following link. You will need version 10.01.51 of the software full version or demo versions, released 20/04/2010 or a newer version.
http://rapidshare.com/files/378438789/SHIFT.001.sprj [2]
Best regards,
Rafael