My Companys role in one project is MEP Subcontractor. GC (General Contractor) suspend all the works in the project due to his disputes with the owner regarding delay penalty which the owner decided to apply to GC and deduct its full amount from the GC next running bill. The suspension period now is exceeding more than 100 days and we dont have any idea when the GC will resume the work in the project.
If Our Contract is not under FIDIC contract and there is no suspension provision in the contract agreement, is there any chance for us as a subcontractor to terminate our contract with GC after this long suspension period then claim him with all related damages?