Dear All,
My schedule has overall duration as 12months. After 4months actual progress deviates from planned dates. Now I want to revise schedule, my consultant told that in new revised schedule actual dates should not be displayed in Early Start / Early Finish columns but those columns should show actual dates without letter "A". More than 1000 of activities already shows progress. Please adivse me how to avoid letter "A" in early / late dates of revised schedule.
Thanks
Venkat
My schedule has overall duration as 12months. After 4months actual progress deviates from planned dates. Now I want to revise schedule, my consultant told that in new revised schedule actual dates should not be displayed in Early Start / Early Finish columns but those columns should show actual dates without letter "A". More than 1000 of activities already shows progress. Please adivse me how to avoid letter "A" in early / late dates of revised schedule.