Gents,
We are looking for an option where we will be able to indicate an inactive period in an activity which is yet to start? For example :
Activity Start : 1-May-10
Activity Finish : 1-Sep-10
Data Date : 1-Apr-10
Inactive period required : 15-May-10 to 15-Jun-10
Can we get any help on this?