I am facing a strange problem in Must Finish by date in P6. My program was originally built in with Must finish date of 23rd July 2012. Later we got instructions to change the must finish date to 24th July 2012. (a day added)
But when i change the must finish date from 23rd July 2012 to 24th July 2012 and reschedule it, P6 calculates my schdule only based on 23rd July 2012 not on 24th July 2012.
I even tried to change Anticipated finish date to 24th July 2012, but still the problem is there. Moreover 24th July 2012 is not an holiday here. i also checked the calendar settings.
But if i change the must finish date as 25th July 2012, P6 calculates my project based on 24th July 2012...Can anyone explain me the reasons......
But when i change the must finish date from 23rd July 2012 to 24th July 2012 and reschedule it, P6 calculates my schdule only based on 23rd July 2012 not on 24th July 2012.
I even tried to change Anticipated finish date to 24th July 2012, but still the problem is there. Moreover 24th July 2012 is not an holiday here. i also checked the calendar settings.
But if i change the must finish date as 25th July 2012, P6 calculates my project based on 24th July 2012...Can anyone explain me the reasons......