I have recently taken over a Programme and I have been asked to illustrate why delays to a specific work package has occurred over the last 13 monthly updates. (This is one work package of 6 in the programme)
Does anyone know a quick report or method of illustrating how the acitivities have moved for the specific work package only? Perhaps coding the acitivities somehow and a group /sort??
P6 only has 3 baselines which it can illustrate graphically so I can’t perform this task visually. Any help would be great.