hi all
it is a common practice to put links between activities just to level resource.
does it make sense to request the removal of all soft logic links when you review a baseline.
can you request from your subcontractor resource loaded baseline, with maximum availability of resources.
ie : automatic leveling is turned on.
please advice.
best regards
the contract is vague, all it say the subcontractor must submit a level 4 program.
it is a common practice to put links between activities just to level resource.
does it make sense to request the removal of all soft logic links when you review a baseline.
can you request from your subcontractor resource loaded baseline, with maximum availability of resources.
ie : automatic leveling is turned on.
please advice.
best regards
the contract is vague, all it say the subcontractor must submit a level 4 program.