I am trying to change the colour of milestones, not started/finished on time, to red.
Basically, I want the Gantt view to what milestones should have been completed by todays date but havent, and what have been completed by todays date.
I have managed to turn completed milestones to green by creating a green milestone in Bar Styles and assigning it to be displayed From: Actual Start and To: Actual Start.
Can anyone help please?????
Thanks, Adam