Dear all,
Iam working on 3B+G+M+18 office floor building project having built up area 45,356m2 and height is 80.60m duration of 21 months.On left side of the building is another building of 53m and distance between the two buildings is 0.6m.The package includes enabling works & construction.
I would like to ask which are the problems faced bcoz of adjacent building and if u all can suggest some solution.
Enabling works : Shoring & Piling works excavation depth upto -14.8m.for shoring (secant piling)
Structure works : Shuttering on left side what is other than traditional formwork alternative for left side
Finishes : Blockwork ,plaster and paint how it will be done.
Please reply asap.
Thanks,
Vrinda.
Iam working on 3B+G+M+18 office floor building project having built up area 45,356m2 and height is 80.60m duration of 21 months.On left side of the building is another building of 53m and distance between the two buildings is 0.6m.The package includes enabling works & construction.
I would like to ask which are the problems faced bcoz of adjacent building and if u all can suggest some solution.
Enabling works : Shoring & Piling works excavation depth upto -14.8m.for shoring (secant piling)
Structure works : Shuttering on left side what is other than traditional formwork alternative for left side
Finishes : Blockwork ,plaster and paint how it will be done.
Please reply asap.
Thanks,
Vrinda.