In Time impact method ,for example Nov 2009 on wards payment was not paid by the client to the general contractor .The programme used to demonstrate the dealy is consented programme of works with cost loaded .
In that case updating the programme up to November and then introducing delay event as payment [ From Nov to JAN 2010] and activities whcih has not started due to delay in payment are tied with the delay event.
Is this way of presenting the delay will be acceptable by consultant ?