Hello,
I have a resource pool of 13. They have been given a task that takes 10 days to complete. Not a problem...however, the current task will require 50 resources and I have only 13. MSProject only shows me that the resources are overloaded. I want the leveling algorithm to show me that it will actually take 40 days to complete.
Days 1-10, 13 resources; days 11-20, 13 resources; days 21-30, 13 resources; and days 31-40, 11 resources.
What am I missing?
Thanks,
Eric
I have a resource pool of 13. They have been given a task that takes 10 days to complete. Not a problem...however, the current task will require 50 resources and I have only 13. MSProject only shows me that the resources are overloaded. I want the leveling algorithm to show me that it will actually take 40 days to complete.
Days 1-10, 13 resources; days 11-20, 13 resources; days 21-30, 13 resources; and days 31-40, 11 resources.
What am I missing?
Thanks,
Eric