Hi guys,
I wonder why my milestones (Finish and Start)dont follow the dates i set-up, everytime i run and schedule, it returns or go-back always to the very start date of my schedule. They supposed to be placed on the dates i scheduled.
Unless i put constraints, then milestones follows.
Im worried about constraints? Do they affect the S-Curve Output?
Can milestones follow my scheduled dates without putting constraints.
Thanks guys and hope to hear your great ideas soon.