Is there a way to edit / add to a baseline in Asta?
With an existing programme, in MS Project (2003), you can add new tasks (ie. compensation events) and add a baseline to just those tasks, without reassigning the baseline to the whole project.
The purpose for this is to create a new target baseline, to compare agreed dates & durations (ie. 1st contract programme + agreed compensation events) with the actual dates & duration.
Or am i going about this in the wrong way?
The contract is NEC3 Option C
With an existing programme, in MS Project (2003), you can add new tasks (ie. compensation events) and add a baseline to just those tasks, without reassigning the baseline to the whole project.
The purpose for this is to create a new target baseline, to compare agreed dates & durations (ie. 1st contract programme + agreed compensation events) with the actual dates & duration.
Or am i going about this in the wrong way?
The contract is NEC3 Option C