Dear Friends
I had asked the same Q before it is not working , i repeat again can Any of Answer me.
1. I have integrated program which has more than 10 projects.
2. Each project in the program are linked.
3. I got the updates from each projects in XER
4. I have imported the projects to the integrated program
5. But the dares are changing when i run program
6. Solution to this would be like in p3 importing from EXCEL is it possible to do in P6 like in p3 exporting as .wk1 file and change & import
regs
anand