I need to change about 2000 Activity IDs because the existing activity IDs in my schedule are longer than 20 characters. I already have the old Activity IDs and corresponding new Activity IDs in excel spreadsheet so I could easily import the new Activity IDs with minimal effort.
I do not want to have to delete all of the activities with the old IDs and create New Activities with New IDs because I will loose all of my logic.
Is there an easier way???