Hi,
When looking at the schedule log I get some warnings / errors concerning "milestones with invalid relationships".
When examining the milestones reported as invalid and those not reported as errors I cant find any specific differences. What Im looking for to correct this issue?
I tried to run a schedule check in Pertmaster/PRA on the same programme and even though also a Primavera product, Pertmaster didnt report anything on "milestones with invalid relationships".
Any suggestions how I can sort out the "invalid milestone"-problem?
Regards,
Bo
When looking at the schedule log I get some warnings / errors concerning "milestones with invalid relationships".
When examining the milestones reported as invalid and those not reported as errors I cant find any specific differences. What Im looking for to correct this issue?
I tried to run a schedule check in Pertmaster/PRA on the same programme and even though also a Primavera product, Pertmaster didnt report anything on "milestones with invalid relationships".
Any suggestions how I can sort out the "invalid milestone"-problem?
Regards,
Bo