Hi,
I have just run a Scheduling/Leveling Report & the Scedule log has provided me with 2 exceptions as per usual these are not found in the primavera help & I cannot find POINT anymore!
The exceptions are:
Activities with unsatisfied constraints? 2 (These seem to be both Mandatory start dates, I have others in the network, but it only seems to be unhappy with 2 of them ? These are all closures, none have any relationships, they all have 7 day calendars) - what is this telling me?
Activities with unsatisfied relationships? 0 - I have 10 activities which are out of sequence in the network (I am on retained logic) but dont think this is what it is unhappy with ! any ideas?
Thanks in advance
Rob
I have just run a Scheduling/Leveling Report & the Scedule log has provided me with 2 exceptions as per usual these are not found in the primavera help & I cannot find POINT anymore!
The exceptions are:
Activities with unsatisfied constraints? 2 (These seem to be both Mandatory start dates, I have others in the network, but it only seems to be unhappy with 2 of them ? These are all closures, none have any relationships, they all have 7 day calendars) - what is this telling me?
Activities with unsatisfied relationships? 0 - I have 10 activities which are out of sequence in the network (I am on retained logic) but dont think this is what it is unhappy with ! any ideas?
Thanks in advance
Rob