Here is what happened to me: I used Global Change to assign Bell Curves to my labor resource. The resource was loaded with budgeted dollars. After applying the Global Change...guess what: all my dollars dissapeared.
My question is: did I do something wrong? Is there any way to recover the data (budgets)? My P6 was downloaded as a stand-alone software, on my personal laptop.
THank you so muh for your answer.
Here is what happened to me: I used Global Change to assign Bell Curves to my labor resource. The resource was loaded with budgeted dollars. After applying the Global Change...guess what: all my dollars dissapeared.
My question is: did I do something wrong? Is there any way to recover the data (budgets)? My P6 was downloaded as a stand-alone software, on my personal laptop.