Gents,
I would like to present baseline bars with progress percentage – same row (the main purpose of doing this to remain the bar as is and at the same time present the progress). But the problem is when I put 25% on percentage column the baseline bars shown 100% completed. Why this happen and what should I do?
I would like to present baseline bars with progress percentage – same row (the main purpose of doing this to remain the bar as is and at the same time present the progress). But the problem is when I put 25% on percentage column the baseline bars shown 100% completed. Why this happen and what should I do?