I have a number of projects in P6. We have linked P6 to Primavera Contracts Manager to show the Schedule % Complete for each project.
Now, the problem is that the %ages displayed in Contracts Manager do not represent the progress values in P6.
Any ideas?
Does anybody know how the Schedule % Complete is calculated??
Response would be appreciated.