Dear Superiors, is there any tactic on the following concern in the P6.2 please!
I am using primavera 6.2 and my schedule is loaded with cost and man hours. My consultant is asking from me to show the particular activities whose Plan and Actual relative weights are ‘X’ of that particular month.
This is what I did in excel while importing the whole schedule and subtracting the activity dates from previous data date to the current data date and converting those in to percentages. But he is asking from the program I mean in Primavera6.2.
Thanking you.
I am using primavera 6.2 and my schedule is loaded with cost and man hours. My consultant is asking from me to show the particular activities whose Plan and Actual relative weights are ‘X’ of that particular month.
This is what I did in excel while importing the whole schedule and subtracting the activity dates from previous data date to the current data date and converting those in to percentages. But he is asking from the program I mean in Primavera6.2.
Thanking you.