Good Day to all!
I want to seek anyones help regarding on how get the planned value cost.
I tried to input actual site percentage in my program but when i update it no value for Planned value cost, only Earned value cost. I need to compare between Planned and earned value..
Here what i did..
1. I input all actual site percentage in the "% Complete column"
2. I updated and change the data date from tools\update progress
3. I went to tools\option and clicked the earned value.
Am I correct what I did or I missed something?
Thank you.
chris
I want to seek anyones help regarding on how get the planned value cost.
I tried to input actual site percentage in my program but when i update it no value for Planned value cost, only Earned value cost. I need to compare between Planned and earned value..
Here what i did..
1. I input all actual site percentage in the "% Complete column"
2. I updated and change the data date from tools\update progress
3. I went to tools\option and clicked the earned value.
Am I correct what I did or I missed something?
Thank you.
chris