Dear All,
I have strange problem while importing the contractors program !
It gives the correct dates when I am importing on the server based database but gives the 3 days duration less, when I am importing on the laptop. If everything is same (same .xer file, same scheduling parameters ) then why is difference in the dates?
Is it due to database structure or I am missing something?
I am using P 6.0 at server and P6.01 version at laptop.
Thanks to all responders in advance.
Regards,
A.S.Shukla