Hello planners,
I have been given a large schedule from a contractor that contains lots of lags (both positive and negative)
I need to better understand these lags so need a global change to allow me to select all activities with relationshsip lags.
I cant find a way to do this ?
Keepo planning,
Kevin.
I have been given a large schedule from a contractor that contains lots of lags (both positive and negative)
I need to better understand these lags so need a global change to allow me to select all activities with relationshsip lags.
I cant find a way to do this ?
Keepo planning,
Kevin.