Hi,
My project has about 3000 activities and has a strange case. Three activities in a row (Act A then Act. B, then Act. C) without any constraints and their Total Float is as follow
Act. A: TF=-1
Act. B: TF=15
Act. C: TF=-1
I wonder if there is an explanation of that case knowing that nothing else is linked to Act. B. I am using P6