Dear Friends,
We are preparing a schedule to be attached with our technical bid for Oil & Gas Tender.
The schedule is prepared in P6 with WBS Structure. We have weightages for all the activities which sums to 100%.
How to draw early and late dates curve in P6 using only weightage available for each activity?
Please dont suggest on usage of resource allocation to each activity, as at tendering stage it is not done in our company. Please excuse.
Regards,
Bharath Kumar J
We are preparing a schedule to be attached with our technical bid for Oil & Gas Tender.
The schedule is prepared in P6 with WBS Structure. We have weightages for all the activities which sums to 100%.
How to draw early and late dates curve in P6 using only weightage available for each activity?
Please dont suggest on usage of resource allocation to each activity, as at tendering stage it is not done in our company. Please excuse.
Regards,
Bharath Kumar J