Please help me on this traditional concrete frame cycle time :
2 core walls, 12 cols and 18m x 12m slab
is 3 weeks from verts start to slab finish sound about right?
Many thanks
Daran
2 core walls, 12 cols and 18m x 12m slab
is 3 weeks from verts start to slab finish sound about right?
Many thanks
Daran