Hi Fox,
Why on earth P6.1 calculates duration percent complete besed on original duration not at completion duration? I am using duration percent complete and whenever my at completion duration and OD have big diffrence the % is screwed and I have to mannually adjust OD for all in progress activites everytime I update the schedule.
1) Is there any way to change the calculation procedures? Any settings in application?
2) OD is based on Planned Dates (Which I hate!!!); sometimes eventhought my OD is equal to at completion duration, because the planned dates are not matching with start and finish date, duration percent complete in the summary bar is not accurate! How can I get rid of these planned dates or make them always equal to start and finish dates? 9Also sometimes my resources stick to my planned dates vs actual start or finish dates)
Appreciated your future solutions if any?!!
Sean
Why on earth P6.1 calculates duration percent complete besed on original duration not at completion duration? I am using duration percent complete and whenever my at completion duration and OD have big diffrence the % is screwed and I have to mannually adjust OD for all in progress activites everytime I update the schedule.
1) Is there any way to change the calculation procedures? Any settings in application?
2) OD is based on Planned Dates (Which I hate!!!); sometimes eventhought my OD is equal to at completion duration, because the planned dates are not matching with start and finish date, duration percent complete in the summary bar is not accurate! How can I get rid of these planned dates or make them always equal to start and finish dates? 9Also sometimes my resources stick to my planned dates vs actual start or finish dates)
Appreciated your future solutions if any?!!
Sean