Good day Gentlemen,
I am having difficulties trying to show an actual resource curve. It seems that every time I update the schedule, and enter new actuals for the resources, the curve changes. It seems to be taking the total actual units that I have chieved upto date and then use the resource curve assigned to it. As a result, I have an actual curve that resembles to the planned curve but with just less or more quantity.
ex:
OD = 10 days
Budgeted units = 1000 (evenly distributed)
Update: Day 2
Actual Units: 100 (100 less than the planned)
Update: Day 4
Actual Units: 400 (300 done within 2 days)
The actual resource curve will show that I have been on time and performing as planned since the beginning.
I hope this is clear enough.
Regards,
Brian
I am having difficulties trying to show an actual resource curve. It seems that every time I update the schedule, and enter new actuals for the resources, the curve changes. It seems to be taking the total actual units that I have chieved upto date and then use the resource curve assigned to it. As a result, I have an actual curve that resembles to the planned curve but with just less or more quantity.
ex:
OD = 10 days
Budgeted units = 1000 (evenly distributed)
Update: Day 2
Actual Units: 100 (100 less than the planned)
Update: Day 4
Actual Units: 400 (300 done within 2 days)
The actual resource curve will show that I have been on time and performing as planned since the beginning.
I hope this is clear enough.
Regards,
Brian