With the risk of this being asked before, but as excuse that the search ain’t working I’m asking this (apparently) simple question.
I’m working an EPC project at the moment and it’s in P6 6.2
Our schedule got approved by the client and I’ve created the first baseline.
I’ve now progressed the current schedule and want to create a S-Curve showing the Early and Late from the baseline and the actual and forecast from the current (as I used to do in P3).
How is this done in P6??
I’m already very disappointed that I can’t assign percentages to the Y2 axis (if I can, please let me know).