Dear PPs
I am newbie here.
2 things i need to know
i... If we prepare a programme in P6, WBS will allocate automatically to each activity or we need to assign it manually ?
If manually then how can we assign this WBS to each activity?
ii.....In P3, in status bar at bottom , following items appear ’Area, Department, Responsibility’ etc but in P6 these items never appear. Only theses appear ‘WBS , Responsible Manager, Primary Resource’ etc
why? ’Area, Department, Responsibility’ do not appear in status bar in P6 as appears in P3
Is this possible to show ’Area, Department, Responsibility’ in status bar at bottom in P6 if we define these in Group and Sort?
Experts please help me out in above.
Many thanks
Steve
I am newbie here.
2 things i need to know
i... If we prepare a programme in P6, WBS will allocate automatically to each activity or we need to assign it manually ?
If manually then how can we assign this WBS to each activity?
ii.....In P3, in status bar at bottom , following items appear ’Area, Department, Responsibility’ etc but in P6 these items never appear. Only theses appear ‘WBS , Responsible Manager, Primary Resource’ etc
why? ’Area, Department, Responsibility’ do not appear in status bar in P6 as appears in P3
Is this possible to show ’Area, Department, Responsibility’ in status bar at bottom in P6 if we define these in Group and Sort?
Experts please help me out in above.
Many thanks
Steve