In order to help you verify your updates SureTrak provides two scripts, Schedrpt.sbl and Sequence.sbx. Sequence.sbx is an executable for an out-of-sequence report, a script not documented maybe because it is part of a Service Pack.
Although P6 provides a schedule report which identifies Unsatisfied Date Constraints, neither Primavera P3 nor Primavera SureTrak does. Therefore I would like your comments for the following logic statements to help me with a script I am trying to develop for SureTrak.
Statements for Date Constraints to be satisfied:
1. Start Constraint (early) ES=>CONSTRAINT DATE
2. Start Constraint (late) LS=< CONSTRAINT DATE
3. Finish Constraint (early) EF=> CONSTRAINT DATE
4. Finish Constraint (late) LF=< CONSTRAINT DATE
5. Start Constraint ES=LS= CONSTRAINT DATE
6. Mandatory Start Constraint ES=LS= CONSTRAINT DATE
7. Mandatory Finish Constraint EF=LF= CONSTRAINT DATE
8. Expected Finish Constraint EF= CONSTRAINT DATE
Statements for the Date Constraints to be unsatisfied:
1. Start Constraint (early) ES 2. Start Constraint (late) LS>CONSTRAINT DATE
3. Finish Constraint (early) EF< CONSTRAINT DATE
4. Finish Constraint (late) LF>CONSTRAINT DATE
5. Start Constraint ES<>CONSTRAINT DATE &/or LS<>CONSTRAINT DATE
6. Mandatory Start Constraint ES<> CONSTRAINT DATE &/or LS<>CONSTRAINT DATE
7. Mandatory Finish Constraint EF<>CONSTRAINT DATE &/or LF<>CONSTRAINT DATE
8. Expected Finish Constraint EF<>CONSTRAINT DATE
Cordially,
Rafael Davila
Although P6 provides a schedule report which identifies Unsatisfied Date Constraints, neither Primavera P3 nor Primavera SureTrak does. Therefore I would like your comments for the following logic statements to help me with a script I am trying to develop for SureTrak.
Statements for Date Constraints to be satisfied:
1. Start Constraint (early) ES=>CONSTRAINT DATE
2. Start Constraint (late) LS=< CONSTRAINT DATE
3. Finish Constraint (early) EF=> CONSTRAINT DATE
4. Finish Constraint (late) LF=< CONSTRAINT DATE
5. Start Constraint ES=LS= CONSTRAINT DATE
6. Mandatory Start Constraint ES=LS= CONSTRAINT DATE
7. Mandatory Finish Constraint EF=LF= CONSTRAINT DATE
8. Expected Finish Constraint EF= CONSTRAINT DATE
Statements for the Date Constraints to be unsatisfied:
1. Start Constraint (early) ES 2. Start Constraint (late) LS>CONSTRAINT DATE
3. Finish Constraint (early) EF< CONSTRAINT DATE
4. Finish Constraint (late) LF>CONSTRAINT DATE
5. Start Constraint ES<>CONSTRAINT DATE &/or LS<>CONSTRAINT DATE
6. Mandatory Start Constraint ES<> CONSTRAINT DATE &/or LS<>CONSTRAINT DATE
7. Mandatory Finish Constraint EF<>CONSTRAINT DATE &/or LF<>CONSTRAINT DATE
8. Expected Finish Constraint EF<>CONSTRAINT DATE
Cordially,
Rafael Davila