Can Open Plan do this?
Resource levelling and mandatory lag
Example.
A work instruction becomes an activity in P6.
Work instruction “a” is an isolation of a piece of equipment.
Work instruction “b” is the work to be performed when the isolation has been performed.
It is essential that the work is performed immediately after the isolation is performed.
A finish-to-start relationship does this very well when scheduling. Unfortunately since there is no “mandatory lag” capability in P6, when the project is levelled, there is no way to ensure that activity “b” follows immediately after activity “a”.
Any Ideas team?
Resource levelling and mandatory lag
Example.
A work instruction becomes an activity in P6.
Work instruction “a” is an isolation of a piece of equipment.
Work instruction “b” is the work to be performed when the isolation has been performed.
It is essential that the work is performed immediately after the isolation is performed.
A finish-to-start relationship does this very well when scheduling. Unfortunately since there is no “mandatory lag” capability in P6, when the project is levelled, there is no way to ensure that activity “b” follows immediately after activity “a”.
Any Ideas team?